Larry M
User Rank
Platinum
Re: No surprise.
Larry M   10/18/2013 12:09:01 PM
NO RATINGS
At the large manufacturing company where I have worked for 45 years, we have always had instrument calbration labs. Every piece of equipment has a sticker indicating when calibration is next due. Employees are not permitted to use equipment beyond the calibration due date or equipment which has bypassed the calibration lab.

Simply applying this process to gauges (and fitting a shut-off valve in series with each gauge) would solve this problem.

Rob Spiegel
User Rank
Blogger
Re: WIKA
Rob Spiegel   10/18/2013 11:24:26 AM
NO RATINGS
You're welcome, Car-Nut. This is an interesting subject, a weak spot at plants, and a dangerous weak spot at that.

Rob Spiegel
User Rank
Blogger
Re: It could blow up a plant
Rob Spiegel   10/18/2013 11:08:56 AM
NO RATINGS
That's right, Chuck. Gauges are usually mechanical, and thus they break. When they break, they don't stop anything. All you lose is your ability to monitor what is happening out of sight. But that could be critical.

Car-Nut
User Rank
Iron
WIKA
Car-Nut   10/18/2013 8:59:41 AM
NO RATINGS
As the Logistics manager for WIKA U.S., I must say it's nice to see an article about our organization. Thanks DN.

Rob Spiegel
User Rank
Blogger
Re: No surprise.
Rob Spiegel   10/17/2013 11:58:30 PM
NO RATINGS
I agree, Ann, you have to take the source of this data into consideration. But even if it's half of the 25%, it's significant. Wika also listed a handful of recent plant explosions and speculated they were caused by failed gaugues. Since it's just speculation, I left it out of the story. But it does make you think.

Rob Spiegel
User Rank
Blogger
Re: It could blow up a plant
Rob Spiegel   10/17/2013 11:52:27 PM
NO RATINGS
Yes, GTOlover, it's hard to replace a gauge under high pressure -- or, if the gauge is way below the water -- as in the BP spill. I can see the potential human error that happens then the engineer looks at two gauges and one reads that everything is OK. The difficulty of dealing with a problem may lead the engineer to assume -- wrongly -- that the gauge showing building pressure is the broken gauge. If the author of the book on the BP spill is correct, that judgment cost lives.

Rob Spiegel
User Rank
Blogger
Re: Network those things
Rob Spiegel   10/17/2013 11:35:06 PM
NO RATINGS
Good point Naperlou. A simple electronic signal -- setting off an alarm on the control side -- when the measurement goes into its red would seem enough, especially if it's backed up by scheduled visual checks to make sure the gauge is working.

Charles Murray
User Rank
Blogger
Re: It could blow up a plant
Charles Murray   10/17/2013 6:14:31 PM
I believe the 25% figure. As much as we at Design News write about modern, networked, electronics technology, we often forget that not every plant is so up to date. Sometimes, if there's no reason to replace something, it gets old, and when it gets old, it often breaks.

Ann R. Thryft
User Rank
Blogger
Re: No surprise.
Ann R. Thryft   10/17/2013 6:02:50 PM
NO RATINGS
25% seems like a relatively huge number, considering what kinds of warnings these gauges provide. That percentage might be high, seeing that it's from a company that makes gauges. OTOH, from what I've read many times, including in the comment sections to various DN articles, gauges in fact don't get monitored often enough, if at all. The BP Horizon example is perhaps the most dramatic recent one.

GTOlover
User Rank
Platinum
Re: It could blow up a plant
GTOlover   10/17/2013 2:39:22 PM
NO RATINGS
Rob, I agree with getting rid of gauges that are not used. But the usefulness of many gauges are not apparent until you have to diagnose and fix an issue with a piece of equipment or plant resource. This is also the time that maintneance guys find out that the gauges are broken or not working correctly.

Part of my strategy was to remove the gauges and place a quick-connect fitting in its place. Then when the need to view a gauge arose, pop one onto the fitting. However, I could see that in some enviroments (like chemical gases/liquids) this may not be appropriate. Also, it is really hard to install a hydraulic gauge onto a fitting under high pressure!

<<  <  Page 2/3  >  >>


Partner Zone
Latest Analysis
McLaren is one of the biggest names in auto racing. But now it has its eyes on a whole new challenge -- innovating healthcare.
What if algae borne of fertilizer runoff that pollutes rivers and lakes could be harvested and used as biofuel feedstock? What if the leftovers could be recycled into farm soil nutrients, eliminating at least some of the need for artificial fertilizers in the first place? Western Michigan University researchers have a plan.
PTC will stream its LiveWrox IoT conference for free beginning Tuesday, May 5.
Manufacturers of plastic parts recognize the potential of conformal cooling to reduce molding cycle times. Problem is, conformal molds require additive manufacturing (AM), and technologies in that space are still evolving. Costs also can be high, and beyond that, many manufacturing organizations lack the knowledge and expertise needed to apply and incorporate additive technologies into their operations.
Stratasys has announced the winners in its 11th annual Extreme Redesign contest for middle school, high school, and college students around the world in engineering, design, and art or architecture.
More:Blogs|News
Design News Webinar Series
3/31/2015 11:00 a.m. California / 2:00 p.m. New York
2/25/2015 11:00 a.m. California / 2:00 p.m. New York
12/11/2014 8:00 a.m. California / 11:00 a.m. New York
5/7/2015 11:00 a.m. California / 2:00 p.m. New York
Quick Poll
The Continuing Education Center offers engineers an entirely new way to get the education they need to formulate next-generation solutions.
May 4 - 8, Designing Low Power Systems using Battery and Energy Harvesting Energy Sources
SEMESTERS: 1  |  2  |  3  |  4  |  5  |  6 |  7


Focus on Fundamentals consists of 45-minute on-line classes that cover a host of technologies. You learn without leaving the comfort of your desk. All classes are taught by subject-matter experts and all are archived. So if you can't attend live, attend at your convenience.
Last Archived Class
Sponsored by Proto Labs
Learn More   |   Login   |   Archived Classes
Twitter Feed
Design News Twitter Feed
Like Us on Facebook

Sponsored Content

Technology Marketplace

Copyright © 2015 UBM Canon, A UBM company, All rights reserved. Privacy Policy | Terms of Service