naperlou
User Rank
Blogger
Opt for multiples
naperlou   1/8/2013 10:14:23 AM
NO RATINGS
Rich, in an application like PLCs it is probably better to opt for multiple units.  This allows the modification of different parts of a plant without affecting others.  PLCs will probably not be the major cost driver.

apresher
User Rank
Blogger
One PLC?
apresher   1/8/2013 2:31:06 PM
NO RATINGS
Given the nature of multi-tasking operating systems and more advanced hardware, I expect the devil is in the details.  What types of tasks must be managed from one platform?  What are the overall hardware and processing resources required, etc. for the complete set of tasks.  I think normally one question is how complicated the application software becomes in terms of maintainability and expandability into the future.  Interesting question.

William K.
User Rank
Platinum
Re: Opt for multiples
William K.   1/9/2013 12:37:15 PM
NO RATINGS
In many instances it is better to have multiple PLCs, especially if the process exists in multiple blocks that are not interwoven. In the brick making example, one controller for mixing, one for forming and handling green product, one for running the kiln and kiln conveyer system, and one for handling the logistics of unloding and storage. On top of other advantages, simpler programming and the ability to run the individual processes manually are major benefits. In addition, if a connon PLC type was selected for all the sections, one spare could provide complete backup capability for a lower cost.

Of course, designing the hand-shake between controllers would be an extra task, but the effort would not be as  much as the advantage gained.

jcbond_mi
User Rank
Gold
PLC System Sizing
jcbond_mi   1/9/2013 2:35:13 PM
NO RATINGS
I'd agree with the idea of there is no simple answer for this.  It always depends on the nature of the application.  You always have to consider things such as  I/O counts, cycle times, physical sizes and areas, failure risks, BUDGET, etc.  High-end PLC's can run multiple control sequences concurrently, you can mount multiple CPU's on a single rack, and I/O networking is a very convenients means for wiring and sharing I/O.

For failure, even if you partition areas of an operation into multiple PLC's, failure of a critical PLC can still hamstring the entire operation.  You still have to plan for operating with a critical failure until the failure can be repaired.  So, you always need a full analysis of the risks.  There will always be the situation that you didn't think of, but you should be prepared for the one you do think of

For my 'tastes', for a simple standalone application where failure is an incovenience (think, say an automated car wash), use the single cheapest controller that will work, with standard wiring.

For larger applications, always plan for the future by leaving cabinet space and power capacity for additional PLC's (possibly by at least leaving panel space for a new rack).  I/O networking (Ethernet/IP, ProfiNet, etc.) make adding I/O much easier...  Also, plan for ethernet access to operations from MES, management, etc.  Once plants get a taste for data, they always want more...

Just my opinion - sorry for no specifics!

Thinking_J
User Rank
Platinum
the other question : custom vs PLC
Thinking_J   1/9/2013 2:54:56 PM
NO RATINGS
"When your only tool is a hammer... all your problems start to look like nails"...

Don't make PLCs your only tool (solution to everything)...


My simplest observations:

- for building automation ... distributed controls (PLC, Custom or specifically made for the application - but for multiple customers/sites) .. the wiring architecture is likely more important than the pieces involved. Unless mutiple campuses are involved (10,000+ I/O points).. then other issues become dominate (software architecture).

- for process automation ... too many variables - depends

- for machine controls.. product volume drives the answer (most of the time). What has changed recently, the volume for custom or semi-custom has a much lower threshold than in the past. I can often make a case for custom solution with volumes of less than 50 units / year. In this environment, having a single (easy to trouble shoot) control board can make field maintenance become a driving factor.

- everything else.. depends

My point: be aware of the ALL the options and DON'T ASSUME TOO MUCH.

Examples:

The costs for each hardware option are changing all the time.

There is a cost to maintaining the software for each option and the assumptions for this cost are changing also. In some systems, a PLC can demand a full time software effort (constantly changing environment). This MAY be better handled with Custom configurable software than custom PLC software. Reason: configuration changes on some software will not require regression testing before being put into place. Just depends.

 

 

Jack Rupert, PE
User Rank
Platinum
Re: One PLC?
Jack Rupert, PE   1/19/2013 5:41:31 PM
NO RATINGS
While I agree with the majority of the posters that there is no one correct answer, I would recommend that the original questioner follow up on the idea presented in the article by Doug Huffman.  A lot of the major PLC manufacturers have a number of options for redundant processors and / or power supplies, depending upon what the most likely failure mode in the plant is.  These can go so far as to include hot redundancy that will automatically keep everything running when one fails.  The cheap and easy course of action (if you can live with some downtime while a tech. takes care of the problem) is just having a spare / programmed processor stored in the cabinet.  I have seen that done with a bit of success as well.

bobjengr
User Rank
Platinum
PLC
bobjengr   1/25/2013 6:27:14 PM
NO RATINGS
I don't do that much work with PLC equipment so I'm basically a rookie at application and installation.  With that being the case:

QUESTION:  Do PLCs often serve as redundant devices?  Can one be a "master" with another the "slave"?   One more, are PLCs ever used for "pilot duty" enabling other pieces of electrical equipment to function; i.e. start/stop? 



Partner Zone
Latest Analysis
Advertised as the "Most Powerful Tablet Under $100," the Kindle Fire HD 6 was too tempting for the team at iFixit to pass up. Join us to find out if inexpensive means cheap, irreparable, or just down right economical. It's teardown time!
The first photos made with a 3D-printed telescope are here and they're not as fuzzy as you might expect. A team from the University of Sheffield beat NASA to the goal. The photos of the Moon were made with a reflecting telescope that cost the research team 100 to make (about $161 US).
At Medical Design & Manufacturing Midwest, Joe Wascow told Design News how Optimal Design prototyped a machine that captures the wing-beat of a duck.
The increased adoption of wireless technology for mission-critical applications has revved up the global market for dynamic electronic general purpose (GP) test equipment. As the link between cloud networks and devices -- smartphones, tablets, and notebooks -- results in more complex devices under test, the demand for radio frequency test equipment is starting to intensify.
Much of the research on lithium-ion batteries is focused on how to make the batteries charge more quickly and last longer than they currently do, work that would significantly improve the experience of mobile device users, as well EV and hybrid car drivers. Researchers in Singapore have come up with what seems like the best solution so far -- a battery that can recharge itself in mere minutes and has a potential lifespan of 20 years.
More:Blogs|News
Design News Webinar Series
10/7/2014 8:00 a.m. California / 11:00 a.m. New York
9/25/2014 11:00 a.m. California / 2:00 p.m. New York
9/10/2014 11:00 a.m. California / 2:00 p.m. New York
7/23/2014 11:00 a.m. California / 2:00 p.m. New York
Quick Poll
The Continuing Education Center offers engineers an entirely new way to get the education they need to formulate next-generation solutions.
Oct 20 - 24, How to Design & Build an Embedded Web Server: An Embedded TCP/IP Tutorial
SEMESTERS: 1  |  2  |  3  |  4  |  5  |  6


Focus on Fundamentals consists of 45-minute on-line classes that cover a host of technologies. You learn without leaving the comfort of your desk. All classes are taught by subject-matter experts and all are archived. So if you can't attend live, attend at your convenience.
Next Class: 10/28-10/30 11:00 AM
Sponsored by Stratasys
Next Class: 10/28-10/30 2:00 PM
Sponsored by Gates Corporation
Next Class: 11/11-11/13 2:00 PM
Sponsored by Littelfuse
Learn More   |   Login   |   Archived Classes
Twitter Feed
Design News Twitter Feed
Like Us on Facebook

Sponsored Content

Technology Marketplace

Copyright © 2014 UBM Canon, A UBM company, All rights reserved. Privacy Policy | Terms of Service